Project Description
Muscat Hills 2 Project
Project Details
Location: Muscat Hills
Area: 98 square meters
Scope of Work
- Procurement and installation of gypsum walls with painting
- Installation of TV and related décor
- Procurement and fabrication of coffee table
- Procurement and installation of glass entrance door
- Procurement and installation of staff office entrance door
- Procurement and installation of AC ducting and insulation
- Electrical wiring for lighting and power outlets
- Procurement and installation of ceiling lighting fixtures
- Installation of management and staff office desks
- Installation of marble sheets
- Procurement and installation of management office décor
- Installation of light strips on office walls
- Ceiling painting
- Thermal insulation
- Installation of CCTV cameras
- Procurement and installation of kitchen hood
- Procurement and installation of kitchen sink
- Closet and cabinet construction
- Design and installation of company logo
- Plumbing system adjustments
Challenges
- Due to the client’s urgency to complete the project, the SIP execution team developed and delivered a precise schedule.
- Given the uneven walls and flooring, final execution was aligned with the detailed plans prepared by the SIP team.
- The project site posed limitations due to noise, dust, and location sensitivity.
- The client had specific preferences regarding the quality and color of the wood materials; after consulting with SIP’s engineering team, the execution timeline was slightly extended to meet expectations.